Poolebay.net was first published in response to the high level of public interest in the major beach replenishment projects of 2005-2007.

Copyright © 2005 - 2015 The Poole Bay Partnership. All Rights Reserved. Privacy Policy & Cookie Guidance. Web design.

Borough of Poole www.poole.gov.uk

Other sources of local coastal information

Standing Conference on Problems Associated with the Coastline Poole & Christchurch Bays Shoreline Management Plan (SMP)

These pages contain only archived material

Storm Repairs 2014 - Shore Road towards Branksome beach

£1.8 million funding awarded to replenish the storm damaged beach between Shore Road & Branksome beach by recycling sand from the Swash Channel, Poole Harbour

Replenishment work was completed on 16th December 2014

Borough of Poole www.boroughofpoole.com YC7894 01 A3 Plan - annotated 950px.png

The original area of beach to be replenished - extended when further funding was announced

Main Contractors Rohde Nielsen of Denmark - www.rohde-nielsen.dk/en

Main Contractor

Rohde Nielsen A/S, Denmark

The Aim

The storms of winter 2013/14 caused a significant loss of sand along this frontage and work was prioritised to ensure the beach was wide enough to protect properties and infrastructure against further winter storms.

The Works

The original project involved pumping approximately 40,000 cubic metres of sand onto a 700m stretch of beach at Shore Road; further funding was awarded about halfway into the project securing further replenishment of beaches towards Branksome beach.

Contractors worked 24 hours a day, 7 days a week to complete the project before Christmas.

Funding

Initially £750,000 of Government funding was awarded to carry out replenishment work at Shore Road. A further £1.2 million was granted in November for further works; by carrying out these further works with the dredger, pipeline and heavy plant already in place is estimated to represent a saving of around £300,000.

The dredge area (shown in yellow). The Swash Channel is dredged as part of Poole Harbour Commissioners ongoing maintenance

Click for a larger image

Short videos from the beach team

Index

At Poole’s FCERM* video channel www.vimeo.com/fcerm


* Flood and Coastal Erosion Risk Management

Project videos at vimeo.com/user34272790

Before

After

Before and After Pictures

Project timings

Works commenced on 3rd November 2014 with delivery of pipes for the sinkerline, to be welded on the beach. The dredger Magni R arrived on 15th November

The dredging / pumping operation started on 19th November. Further funding was announced on 27th November, allowing an extension to the project.

Works were completed on 16th December with the area of replenished beach stretching from Sandbanks rock groyne to the end of the beach huts at Canford Cliffs. The project delivered a total of 139,000 cu.m. of sand over a period of 28 days. Four days were lost to the weather, and two to a mechanical problem.

The beaches were clear of pipes and machinery by 15th January 2015.

Thank You

We would like to thank everyone who has visited the beach during this project - for your understanding and patience when we have had to close sections of the beach for safety reasons.  

We would also like to thank the many, many people who have taken an interest in the works, have stopped on the beach to ask us questions about the project, or have viewed this website.